Irvine, CA – November 29, 2016 – WesPac Midstream – Vancouver LLC (WesPac) today received approval of the Application Information Requirements (AIR) from the British Columbia Environmental Assessment Office (BC EAO).

 
 

Irvine, CA – November 29, 2016 – In the latest step toward development and construction of its WesPac LNG Marine Jetty at Tilbury Island, WesPac Midstream – Vancouver LLC (WesPac) today received approval of the Application Information Requirements (AIR) from the British Columbia Environmental Assessment Office (BC EAO). The AIR specifies the information that WesPac is required to provide in its Application for an Environmental Assessment Certificate under the BC Environmental Assessment Act and the Canadian Environmental Assessment Act.

The 18 month process resulting in approval of the AIR involved receiving input from, and review by, many federal, provincial, and local agencies as well as 13 First Nations and the public. The process was conducted by the BCEAO, with WesPac responsible for incorporating relevant input into the AIR.

With the AIR approved, WesPac now moves on to preparing the information specified in the AIR document to make its Application. Although the BC EAO requires completion of the Application within three years, WesPac plans to complete it in 2017.

WesPac’s LNG Marine Jetty Project will be a single-berth dock located on the Fraser River, serving mid-scale and small-scale LNG vessels. Its location will be adjacent to the Tilbury LNG Plant, a separate company owned by FortisBC Energy Inc.

The AIR documents can be accessed through the BC EAO’s Project Information Centre (e-PIC) at http://a100.gov.bc.ca/appsdata/epic/html/deploy/epic_project_home_435.html .

 

About WesPac Midstream LLC

WesPac Midstream – Vancouver LLC is a wholly owned subsidiary of WesPac Midstream LLC, a private energy infrastructure company founded in 1998 to develop, own, and operate energy facilities throughout North America. WesPac is majority owned by Kealine LLC, a private development company.

 

WesPac Tilbury Marine Jetty Project Open House and Invitation to Comment

 
 

 
 

WesPac has reduced its estimate of the maximum number of vessel trips to 124 per year. This includes both bunkering vessels as well as LNG carriers. More details can be found on the BC EAO website

The Canadian federal government requires a federal environmental assessment and approves the British Columbia provincial government’s request for substitution of the environmental assessment for the Project.

 
 
The Canadian Environmental Assessment Agency has determined that a federal environmental assessment of the WesPac Tilbury Marine Jetty Project (the Project) is required pursuant to the Canadian Environmental Assessment Act, 2012. The federal Minister of the Environment has also approved BC’s request for substitution of the environmental assessment for the Project.
 
The federal Minister of the Environment also established a condition requiring the assessment of environmental effects from marine shipping activities associated with the Project, and beyond WesPac’s care and control, along the designated shipping route between the Project’s marine terminal and the pilot station at Sand Heads in her approval of BC’s request for substitution.
 
 
The announcement can be viewed from the following links:

Notice of Determination: http://www.ceaa-acee.gc.ca/050/document-eng.cfm?document=101961
Notice of Commencement/Notice of Substitution: http://www.ceaa-acee.gc.ca/050/document-eng.cfm?document=101960

WESPAC FILES PROJECT DESCRIPTION WITH FEDERAL AND PROVINCIAL ENVIRONMENTAL AGENCIES TO INITIATE ENVIRONMENTAL REVIEW PROCESS

 

Wespac filed a project description on May 11, 2105 for its proposed WesPac Tilbury Marine Jetty Project with Federal and Provincial environmental agencies to initiate the environmental assessment process. This process is estimated to take 15 months and will provide a thorough environmental review and allow for public consultation and input from the public and first nations.

The Canadian Environmental Assessment Agency announced a 20 day federal comment period on the WesPac Tilbury Marine Jetty Project was announced on May 22, 2015. The announcement consists of a news release, public notice and the posting of the project description summary on the Canadian Environmental Assessment Registry internet site (Registry reference number 80105). CEAA sent out notices to relevant parties and first nations asking for comments on two questions: should a federal environmental assessment be performed and should CEAA defer to BCEAO to prepare one Environmental Assessment covering the requirements of both CEAA and BCEAO (a process called substitution). Comments on those two questions are due to CEAA by June 11th

 

You can view the documents from the following links:

News release: http://www.ceaa-acee.gc.ca/050/document-eng.cfm?document=101689

Public notice: http://www.ceaa-acee.gc.ca/050/document-eng.cfm?document=101688

Summary of the project description: http://www.ceaa-acee.gc.ca/050/document-eng.cfm?document=101699

Information about the project on the BCEAO web site can be found at: http://a100.gov.bc.ca/appsdata/epic/html/deploy/epic_project_doc_list_435_p_pro.html

NATIONAL ENERGY BOARD OF CANADA APPROVES WESPAC MIDSTREAM LNG EXPORT LICENSE

Irvine, CA, U.S.A.: On May 7, 2015, WesPac Midstream – Vancouver LLC (“WesPac”) received notification from Canada’s National Energy Board (“NEB”) of its decision to grant WesPac a license to export natural gas from Canada. WesPac submitted an application in June 2014. The license is for a maximum annual volume of 4.76 billion cubic meters of natural gas (equivalent to approximately 3.5 million tonnes of LNG per annum), and is for a term of 25 years. The NEB decision is subject to the approval of the Governor in Council.

A link to the NEB’s announcement about the license decision is found here:

http://news.gc.ca/web/article-en.do?mthd=tp&crtr.page=1&nid=972719&crtr.tp1D=1

WesPac’s export of natural gas will be in conjunction with the WesPac Tilbury LNG Marine Jetty Project currently under development. WesPac’s jetty will be adjacent to the FortisBC Tilbury LNG Plant in Delta, B.C. and will be designed to load LNG cargo into customers’ small and medium-sized LNG carriers as well as LNG barges, one vessel at a time.

WesPac submitted its Project Description to initiate the environmental assessment process in April of this year. It was submitted to both the British Columbia Environmental Assessment Office (BCEAO) and the Canadian Environmental Assessment Agency (CEAA). The anticipated start of operations for the jetty project is the first quarter of 2018.

MINISTER RESPONDS TO VANCOUVER-BASED EXPORT REQUEST

Victoria, BC – June 25, 2014 – Minister of Natural Gas Development Rich Coleman has issued the following statement:

“British Columbia’s LNG potential is growing and creating opportunities for companies in our province.

“WesPac Midstream – Vancouver LLC (WesPac) is the latest company to submit an export request with Canada’s National Energy Board.

“Our province has a vast supply of natural gas to support expansion and energy demands. WesPac will work with FortisBC to build an LNG operation near Vancouver that will serve both domestic and international needs.

“On behalf of the Province of British Columiba I would like to welcome WesPac to those looking to export clean energy to the Asia, creating jobs and new economic opportunities here at home.”

NEB Application To Export LNG from Canada

Irvine, CA – June 24, 2014 – WesPac Midstream – Vancouver LLC (WPMV), a subsidiary of WesPac Midstream LLC (WesPac), has submitted an application to the National Energy Board of Canada for a licence to export LNG sourced from the Tilbury LNG Plant owned by FortisBC Energy, Inc. The Tilbury LNG Plant has recently begun work on an expansion project, which was approved by the BC Government in 2013. The applied-for export licence would cover potential regional exports to customers such as small power plants and bunkering (i.e. fuel) for marine vessels. These customers would benefit from both fuel cost savings, as well as air emissions reductions, by displacing oil-based fuels with natural gas.

WPMV is planning a new marine terminal in the Fraser River adjacent to the Tilbury LNG Plant to accommodate exports of LNG by barges or ships.  The marine terminal would be a single jetty structure providing berth space for one barge or ship, and its size is consistent with other similar structures in the Fraser River.  It will be located on the site of an abandoned marine terminal in previously dredged waters. WPMV is currently conducting engineering and related shipping studies,to prepare for First Nations and public consultation, as well as various applications to government agencies.

 About WesPac Midstream LLC

WesPac is a private energy infrastructure company founded in 1998 to develop, own, and operate energy facilities throughout North America. WesPac is majority owned by Highstar Capital, an independent infrastructure investment firm with a value-added, operational approach and deep expertise in energy investing and development, and WesPac Energy LLC, a private development company.